10 Feb What if I want to buy a plot of land and build my own home?

The planning regulations on Corfu are complicated and at the moment subject to a number of changes. In all cases a building permit must be obtained and this service is normally carried out by a state registered engineer who, in conjunction with you, will complete the plans of the proposed house and submit these together with the other information required to the building permit office for approval.

The engineer would also make an application on your behalf for connection to the electricity and water supplies. Outside the town, most sewage is dealt with by onsite septic tanks.

Once the building permit is obtained, the normal practice is for you to enter into a fixed price building contract with the engineer to build the house. The process of obtaining the building permit normally takes a few weeks and depending on the site, the building process itself can then take a further 9 to 15 months.